Lima Metro Line 2

more than a subway...a new reality for Lima

«Lima without traffic jams? Metro Line 2 has come for it... it will take you to your destination, in a sustainable way... faster and safer travel is possible, while reducing the carbon footprint in this beautiful city.»
Line 2 of the Lima Metro is underway! The 34.5 km tunnel linking the districts of Ate and Callao will be an exciting and efficient journey through 35 stations that a professional and dedicated team has been commissioned to excavate using two TBMs. With 30 months of pre-studies and daily monitoring of the excavation, we ensured stability and peace of mind at the work front. We committed to building a brighter and more connected future for Lima and we succeeded!

The Consorcio Constructor Metro 2 Lima (CCM2L), formed by the companies Salini-Impregilo, Dragados, FCC and COSAPI, responsible for the construction of Line 2 and the Faucett Avenue - Gambetta Avenue branch line (future Line 4) of the Basic Network of the Lima and Callao Metro, which will connect the districts of Ate and Callao, from the east to the west of the Peruvian capital, has commissioned Lombardi to provide on-site technical assistance for the excavation monitoring of the 2 TBMS used for the materialization of the tunnels.

The project, with a total investment of more than US$ 5.6 billion, comprises a total tunnel length of 34.5 km, of which 26.5 km correspond to Line 2, with a total of 27 stations, and 8 km correspond to the Line 4 branch, with a total of 8 stations.

The TBMs, 10.20 m in diameter, work in a Lima gravel soil (GP-Sf) with a grain-supported structure and the presence of boulders, which makes soil conditioning and special treatments necessary to ensure safe progress, protecting the equipment and existing infrastructure on the surface.

To meet these objectives, Lombardi has developed the analysis and verification of the stability and pressure in the excavation face, the definition of the modes of operation with working pressures of the TBMs in the entire longitudinal and geotechnical profile of the tunnel, the definition of the safe points for the revisions of the cutting head, the analysis of the entrances and exits of all the stations and zenith shafts, the monitoring and analysis of the excavation in both TBMs during the whole operation, the study of materials in the laboratory, the intervention project of soil consolidation and treatment for the TBM start-up and the development of special interventions to secure the TBMs in their crossing with important interferences.

Competences
  • Conventional and TBM tunnelling
  • Urban tunnel, metro
  • Geo-Engineering
  • Monitoring
  • Advanced numerical modelling
  • Risk Analysis
35

stations

34.5

km of tunnels

5.6

billion dollars of investment

2.4

million citizens benefited

Lat: -12.06211
Lng: -77.03653

Lima, Peru

230828 Metro de Lima Syomik PE QWQ
«This project presented us with many challenges. Lima's soil is very particular and required us to be aware of every step the machines took in this subsoil. The Consortium's openness allowed us to innovate and meet the objective of providing connectivity to the city.» Artem Syomik – Service leader